TWYN YR ODYN MERTHYR

WRW were responsible for the construction of 24 new affordable homes on the site of a former primary school in Merthyr Each home was designed and constructed to achieve Code for Sustainable Homes Level 3.
The works involved the demolition of the existing school and associated remedial works.

In addition to the delivery of the new houses we also provided infrastructure including; new road / footpaths with associated drainage, road marking, street lighting, landscaping and planting, pumping station, retaining boundary walls and the provision of all new utility services.

CLIENT:
Hendre

VALUE:
£3m

CONTRACT:
JCT Design and Build

ARCHITECT:
Pentan
CIVIL AND STRUCTURAL ENGINEER:
Clarkebond